Below are the key activities for the AQ 2009 Project.
AQ calculation process for Small Supply Points |
26th March - 11th April |
AQ calculation process for Large Supply Points |
1st May - 15th May |
Small Supply Point and Threshold Crosser T04 Files sent to Industry |
19th - 30th May |
Small Supply Point AQ Amendment Window Opens |
1st June |
Start of BSSOQ Review Process |
8th June |
Large Supply Point T04 Files sent to Shippers |
20th - 30th June |
Large Supply Point Amendment Window Opens |
1st July |
First release of MOD81 |
1st July |
BSSOQ Files sent to Shippers |
10th July |
AQ Appeals Window Closes |
31st July |
Second release of MOD81 |
3rd August |
Final day of Shipper Amendment files |
13th August |
Offer addenda process |
29th August - 30th September |
EUC files sent to Shippers |
1st September |
IX NRO/NRL files sent to Shippers |
10th September |
AQ Appeals Window Opens |
14th September |
Delay in producing TRF/MRI files |
23rd - 25th September |
Final AQ implemented - Go Live |
1st October |
Outage on IAD system |
1st October |
Delay in producing TRF/MRI files |
2nd - 5th October |
Final release of MOD81 |
30th October |