Below are the key activities for the AQ 2010 Project.
AQ calculation process for Small Supply Points |
26th March 2010 |
AQ calculation process for Large Supply Points |
3rd May 2010 |
Small Supply Point and Threshold Crosser T04 Files sent to Shippers |
28th May 2010 |
Small Supply Point AQ Amendment Window Opens |
1st June 2010 |
Start of BSSOQ Review Process |
14th June 2010 |
Large Supply Point T04 Files sent to Shippers |
30th June 2010 |
Large Supply Point Amendment Window Opens |
1st July 2010 |
First release of MOD81 |
1st July 2010 |
BSSOQ files released to Shippers |
9th July 2010 |
AQ Appeals Window Closes |
31st July 2010 |
Second release of MOD81 |
1st August 2010 |
Final day of Shipper Amendment files |
13th August 2010 |
Offer addenda process |
28th - 29th August 2010 |
IX NRO/NRL files sent to Shippers |
14th September 2010 |
AQ Appeals Window Opens |
14th September 2010 |
AQ Implementation - Go Live |
1st October 2010 |
Final Release of MOD81 |
1st November 2010 |